Circular shafts
Japan - 1990





Akashi bridge


General view of bridge during construction

Site during excavation of circular diaphragm wall



Typical section of anchoring block


The Akashi bridge links Hongshu island (japan main island) to Shikoku island in the south. The suspension bridge has 3,910 m total span, 1,990 m central span, 2 piers at sea, 2 bank abutments.

Construction of a circular diaphragm wall which will be used as a bank abutment and an anchoring block for the bridge suspension cables.

The inner diameter of the circular diaphragm wall is 85 m, the thickness of the wall is 2.20 m and its depth is 75.50 m.
Equipment used: 2 HF 12,000 Hydrofraises.


















Specialities used

Reinforced concrete diaphragm wallsReinforced concrete diaphragm walls