Design and construction of 6-floor 430 place underground car park.

Soletanche Bachy was in charge of the complete project, from site selection to final works completion:

- representations to the Major Developments Agency of the Paris City Council (the ultimate owner of the asset),
- design, with support from an architect for submitting the permitting application,
- financial package for the whole operation (construction, operation, interest payments),
- engineering to solve all the problems associated with the site,
- construction of structural support and civil works.



General description
130m long, 15m wide (except for end spirals) and 19.50m deep, the car park under the Boulevard Saint-Michel extends from Place Saint-Michel near the river Seine to Boulevard Saint-Germain, fitting snugly in between the Paris Metro, RER rapid transit underground railway and the buildings flanking the Boulevard.

In addition to coping with the lack of street-level space for the work, the design and construction scheduling had to meet other requirements:
- Road traffic had to be maintained along the Boulevard Saint-Michel, which is a red route, as well as pedestrian traffic.
- The trees standing within the car park site along one side of the Boulevard had to be preserved intact.
- Provision had to be made for incorporating an existing telephone cable tunnel passing through the third car park level.

A further constraint was to allow archaeologists to dig to a depth of 6 metres behind a Berlin wall (steel soldier beams and timber lining). Among the many finds was an ancient road paved with limestone blocks, older than the Gallo-Roman city of Lutetia (modern-day Paris).

Description of works
Construction procedure
The retaining wall around the excavation is a diaphragm wall, 0.63m thick and 25m deep, with its toe embedded in a coarse-grained limestone bed. It was built with a Latine Hydrofraise rig, the machine most suited to the cramped conditions (small working area, closely-spaced trees and limited headroom under trees) and capable of digging through hard ground (marl and stone, and coarse-grained limestone).

A grout curtain extends 8m downwards from the diaphragm wall toe, into the limestone, to reduce underseepage and pumpage during construction and operation (the 6th level floor raft is drained).

Where the telephone cable tunnel passes through, a grout curtain and wall built during excavation replaces a section of the diaphragm wall. Trees encroaching on the cover slab were "potted," by inserting horizontal steel pipes in drilled holes under the root systems, the pipes being embedded at one end in the diaphragm wall, and attached to the cover slab ribs at the other.

The diaphragm wall, grout curtain, in situ cover slab, temporary support and the few prefounded columns were built in two phases, in order to maintain traffic along the Boulevard Saint-Michel. Subsequently, the ribbed floor slabs were built by the top-down method. The spiral access ramps at each end were built after completion of the excavation work.

A310.pdf


Techniques

Civil engineering

Regardless of site size, and providing it involves a significant proportion of works in the ground, Soletanche Bachy will handle the complete project, and all aspects of the works, including site supervision, excavations, foundations, civil engineering and all construction operations.

Diaphragm wall

A diaphragm wall is a reinforced concrete wall that is made in situ. The trench is prevented from collapsing during excavation, reinforcing and casting by the use of supporting bentonite slurry. The slurry forms a thick deposit (the cake) on the walls of the trench which balances the inward hydraulic forces and prevents water flow into the trench. A slurry made of polymers can also be used.

Ouvrages

Underground car parks

Soletanche Bachy undertakes the whole of a project from feasibility studies, through design to the complete construction on a turnkey basis.

Urban excavations

Major urban excavations are one of the specialist activities of Soletanche Bachy. Such excavations are required for basements to buildings that are usually part of the foundations of the structure and also used for under-street car parks, cut and cover tunnels for roads, rail, metro and storm water tank...


Voyage au coeur de l'ingénierie de pointe

Find out more about our expertise by: